Energy
Recognizing the growing energy needs of Pakistan, and to overcome the existing deficits, CPEC has allocated a major proportion of its funds to energy generation and transmission.
The projects stated below are included in CPEC and would contribute towards the sustainable growth of industries and unhindered electric supply for domestic consumption in Pakistan.
70%
Project Name | Company Name | Status | Progress | |
Prioritized/Early Harvest Projects, 10400 MW | ||||
2x660MW Port Qasim Coal-fired Power Plant | Power China Resources Ltd. | Completed |
100% |
Project details |
2x660MW Sahiwal Coal-Fired Power Plant | Huaneng Shandong Ruyi (Pakistan) Energy (Private) Ltd. | Completed |
100% |
Project details |
4x330MW Engro Thar Coal-fired Power Plant and Surfice Mine in Block II of Thar Coal Field | China Machinery Engineering Corporation(CMEC) | Completed |
100% |
Project details |
50MW Dawood Wind Farm | Hydrochina International Engineering Co. Ltd. | Completed |
100% |
|
900MW Quaid-e-Azam Solar Park in Bahawalpur | Zonergy Company Ltd. | Completed |
100% |
Project details |
100MW Jhimpir Wind Farm | UEP Wind Power (PVT) Ltd. | Completed |
100% |
Project details |
50MW Sachal Wind Farm | Hydrochina International Engineering Co. Ltd | Completed |
100% |
|
720MW Karot Hydro-Power Project | China Three Gorges South Asia Investment Ltd. | Under Construction |
50% |
Project details |
873MW Suki Kinari Hydropower Project | China Gezhouba Group Corporation International Ltd. (CGGC) | Under Construction |
50% |
Project details |
50MW Sachal Wind Farm | China Sunec Company | Completed |
100% |
|
Thar Mine Mouth Oracle Power Plant ( 1320MW) & surface mine | Shanghai Electric | To be inaugurated |
50% |
Project details |
2 x 660MW Hubco Coal Power Plant | China Power International Holding Ltd. | Completed |
100% |
|
300MW Imported Coal Based Power Project At Gwadar, Pakistan | TBD | NEPRA tariff determination in process |
20% |
Project details |
Matiari-Lahore Transmission Line | China State Grid | Financial Close Achieved |
50% |
|
Actively Promoted Projects, 17045 MW | ||||
1100MW Kohala Hydro-Power Station | China Three Gorges South Asia Investment Ltd. | Negotiation in Process |
15% |
Project details |
Cacho 50MW Wind Power Project | Cacho Wind Energy Pvt. Ltd | Independent Power Producer (IPP) |
LOI Stage |
|
Western Energy (Pvt.) Ltd. 50MW Wind Power Project | Western Energy (Pvt.) Ltd | Independent Power Producer (IPP) |
LOI Stage |
|
Azad Pattan Hydel Project, AJK | China Gezhouba Group/ Larab Group | Independent Power Producer (IPP) |
Expected commercial operation date (COD) 2026 |
|
CPEC-Potential Energy Projects | ||||
Phandar Hydropower Station | — | Under review of experts from both sides |
— |
|
Gilgit KIU Hydropower | — | Under review of experts from both sides |
— |